US 75 Expansion Project

Project Description: Expansion of US 75 from Melissa Road to just north of FM 455. The project includes a redesign of the interchange and bridge over the highway.

Project Status: The project is currently under construction. Utility relocations are still in progress as part of the project.

Contractor(s): TxDOT project.  Contractor Austin Bridge and Road

Project Cost: $79 million

Funding Source:
  TxDOT

Additional Information:

  • The contract for the project (US 75 expansion including the interchange and the bridge) was signed on March 16, 2016.
  • The project time to completion is 884 days per the contract. This is based on 26 working days per month for a total anticipated project time of 34 months.   
  • The City has approximately 2.25 miles of water lines that are being relocated as part of the project.
  • The Anna City Council recently approved an Inter-local Agreement (ILA) with Collin County related to funding for the Utility Relocation Project.
  • The project phasing is subject to change but is expected to be as follows.

- The contractor has begun work on the first half of the FM 455 bridge.
- The contractor will begin work on the Throckmorton bridge and the service road bridges
                  over Throckmorton Creek (This section is in Melissa).
- The contractor will begin installation of temporary asphalt lanes near the main lanes so                        that traffic can be moved off the area where the future main lanes will be constructed.


City of Anna • 111 N. Powell Parkway, P.O. Box 776 • Anna, TX 75409-0776 • Ph. (972) 924-3325 • Fax. (972) 924-2620
Home Home  |  Email Page Email Page  | Print Page Print  |  Calendar  |  FAQs  |  Contact Us  |  Accessibility  |  Site Map |  

Website Policy  |  Renewable Energy Windpowered | Powered by CivicPlus  | Copyright Notices