Due to weather over the weekend, the freeway closure for Aug 22nd thru Aug 23rd has been postponed until Monday Aug 27th 9:00 PM to Tuesday August 28th 6:00 am, weather permitting.
_________
News Release Purpose Total freeway closure for Northbound and Southbound main lanes US 75 at Throckmorton Road.
Closure Dates/Duration – Wednesday, August 22nd, from 9:00 PM until Thursday, August 23rd, at 6:00 AM
Detour Directions:
Friday: All traffic will be required to exit NB US 75 at exit 47 and will be allowed to re-enter at on-ramp north of the bridge at Foster Crossing / Outer Loop. All traffic will be required to exit SB US 75 at the exit north of Foster Crossing / Outer Loop and allowed to re-enter at on-ramp south of Melissa Road.
Situation/Activity
TxDOT’s contractor Austin Bridge and Road will be setting bridge beams at Throckmorton Road over US 75 mainlanes NB and SB.
What is TxDOT doing?
TxDOT will be inspecting the work.
What can the public do?
Be attentive to signage & slow down through work zone. (Local Traffic) Seek Alternate Route