Parks Capital Improvement Projects

Active projects

Click on the name of the project below to read more about the project scope and status. 

  1. Bryant Park 
  2. Finley Park (formerly known as Anna Crossing Park)
  3. John Flavel Greer Park
  4. Carol Park
  5. Slayter Creek Park Playground Replacement
  6. Park System Master Plan Update

History: Soccer goals have been assembled and delivered to the site. The fence installation has been completed. Soil has been tilled and seeded. A park sign has been ordered but no firm ETA on arrival, yet. Staff anticipates the sign may arrive in December. 

Phase II Scope: Install chain link fence and soccer goals at Bryant Park to activate the park as a multi-use practice facility. A contract with a consultant was approved in February 2024 to begin Phase II. 

FY 23/24, Q2 Status: Dunkin Sims Stoffels was contracted to develop a master plan for the park and assist with budget development for Phase II. The kickoff meeting was held in February 2024, and a master plan should be completed by June 2024.

Status as of February 2024:  A kick-off meeting for the development of a master plan for the park was held on Feb. 21. A consultant will assist with the development of a project budget. 

Update July 2024: A consultant is continuing to develop multiple concepts to be presented. 

Update August 2024: Our staff met with the consultant to complete the final review of the master plan. Once the master plan is approved, the city will proceed to contract and develop the construction drawings.

Update November 2024: The Parks Board unanimously approved the final draft of the Bryant Park Master Plan and recommended proceeding with final design documents. 

Update December 2024: City Council will review the final draft and consider approval of the design contract at the Dec. 17, 2024 meeting. 

Update April 2025:  Design is in progress, with potential adjustments being considered for the driveway layout. 

Update August 2025:  The landscape architect has been cleared to proceed with the development of construction documents based on a revised master plan. The project is scheduled to bid in Spring of 2026. Consruction of the project will be scheduled to have the least impact operations at J.K. Bryant Elementary School.

Bryant Field Layout